Nov 8, 2017

By Tyler Freiberger 

Untimeliness is one of the most common reasons protests of government solicitations and awards before the Government Accountability Office (“GAO”) and The Court of Federal Claims are dismissed. The accompanying chart describes the somewhat harsh and complex rules required for filing before each body. For protests on how a solicitation is written, a contractor must protest simply before the bids are made. But other protests have strict timing demands measured from when the basis for the protest “is known or should have been known.” 4 C.F.R. 21.2. The definition of this phrase has been stretched repeatedly to include situations that would likely surprise unwary contractors.

Last year, the GAO decided VMD Systems. The merits of the protest are not particularly interesting, but the decision does illustrate how liberally the GAO is willing to interpret “should have known.”  In VMD Systems, the contractor was excluded from the competitive range of a NASA contract. Hoping to learn as much as possible for why the award would go to another, the contractor elected to receive a debriefing from the government agency after the award was made, rather than a debriefing only on why it was excluded. After the debriefing, VMD protested its exclusion from the process claiming it was held at a higher standard than others. No dice. The GAO ruled that because VMD could have learned the basis of their protest by electing to take the earlier debriefing option, waiting until after VMD actually knew of the basis was untimely, and therefore the protest was dismissed.

More recently, the Court of Federal Claims used similar logic to that applied by the GAO in VMD Systems. In Sonoran Technology, the Court of Federal Claims considered an odd set of events where one contractor, Sonoran, won the award, faced two different protests, lost the protest and then ultimately the award to a competitor.  As the original awardee, Sonoran had the right to intervene in the original protests but chose not to. When the award was eventually given to the competitor, Sonoran filed a protest of its own through a complaint to the Court of Federal Claims.  The court dismissed the complaint as untimely under the same reasoning used in VMD Systems; had Sonoran exercised the right to intervene in the original protests, it would have learned the basis for the complaint to the Court of Federal Claims much earlier therefore that is the date where the timeliness clock starts.

So, what can a contractor do to protect his or her rights? The accompanying chart provides a summary of important rules and procedures required to protest before the GAO and the Court of Federal Claims. But as shown here, the deciding bodies often interpret the rules to require contractors to aggressively seek out any information that could support a protest and act immediately.

About the Author:

Tyler Freiberger Headshot | Centre Law & Consulting in Tysons, VA Tyler Freiberger
Associate Attorney

Tyler Freiberger is an associate attorney at Centre Law & Consulting primarily focusing on employment law and litigation. He has successfully litigated employment issues before the EEOC, MSPB, local counties human rights commissions, the United States D.C. District Court, Maryland District Court, and the Eastern District of Virginia.

 

 

Share on FacebookShare on LinkedInTweet about this on TwitterEmail this to someone

Leave a Reply

Your email address will not be published. Required fields are marked *