Jun 22, 2017

In a decision publicly released on May 30, 2017, Alphaport Inc. – Reconsideration, B-414086.3 (May 23, 2017), the GAO denied a request for reconsideration regarding a nearly $25 million contract. The GAO originally denied Alphaport, Inc.’s bid protest challenging the National Aeronautics and Space Administration’s (NASA) award of a contract to Banner Quality Management, Inc. for technical support services.

The solicitation was awarded as a single cost-plus-fixed-fee contract based on best value, focusing on three evaluation factors: technical capability, cost/price, and relevant experience and past performance. Regarding the cost factor, the solicitation stated that evidence of an approved accounting system would be required for award of the contract. Evidence of the approved accounting system would be shown by submitting four specific documents.

Alphaport initially challenged the award to Banner by alleging that the solicitation contained a material requirement to submit certain documentation to demonstrate the acceptability of the offeror’s accounting system. Despite NASA finding Banner’s accounting system acceptable, Banner only submitted three of the four required documents. Alphaport sought reconsideration after the GAO determined that the agency’s evaluation and selection decision were reasonable and consistent with the terms of the solicitation.

Specifically, Alphaport argued that the GAO erroneously concluded that the agency’s evaluation was reasonable because the adequacy of an accounting system is generally a matter of responsibility. In denying the request for reconsideration, the GAO reminded Alphaport that its decision already addressed its allegation that the agency waived a material requirement of the solicitation when it concluded that the solicitation’s material requirement was for an acceptable accounting system rather than specific documentation. Indeed, the GAO noted that Alphaport did not actually challenge the adequacy of Banner’s accounting system but only that the agency did not comply with a material RFP requirement. The GAO found no error of law and instead found that Alphaport merely disagreed with its determination.

 

About the Author:

Heather Mims | Centre Law & Consulting in Tysons VA Heather Mims
Associate Attorney

Heather Mims is an associate attorney at Centre Law & Consulting. Her practice is primarily focused on government contracts law, employment law, and litigation. Heather graduated magna cum laude from the George Mason School of Law where she was the Senior Research Editor for the Law Review and a Writing Fellow.

 

Share on FacebookShare on LinkedInTweet about this on TwitterEmail this to someone

Leave a Reply

Your email address will not be published. Required fields are marked *